Sequence of Work (schedule subject to change based upon weather and productivity)
Day 1: Leveling course on concrete section (Manchester to Irene) and at St. Clement’s church, then start surface course at Manchester
Day 2: Northbound lane from Manchester to Doubletree
Day 3: Southbound lane from Doubletree to Manchester
Day 4: Aprons at side streets